Rosti Infrastructure Upgrade 11kV

Rosti:

Due to the continued success of the Rosti facility in Larkhall the facility was expanding it’s operations, this required a fundamental review of the existing HV and LV equipment.

Labron Technical Ltd undertook an extensive review of the site HV and LV inventory before designing a complete new electrical infrastructure to suit both the factories current needs and the predicted growth.Rosti PNG

Acting as client’s agent Labron Technical Ltd prepared technical specifications for the new equipment, provided tender documentation, vetted technical and commercial offers on behalf of Rosti Technical Plastics and assisted with the selection of the main electrical contractor. Throughout the project Labron Technical Ltd ensured compliance with general and factory specific H&S requirements, ensured quality and program were maintained and provided technical support as well as liaising with Scottish Power to organise and manage the outage program.