Nestle Intake Substation 33kV

Nestle:

Labron Technical Ltd were delighted to be asked to assist Nestle with the review of subcontractor design documentation in relation to the electrical infrastructure works that took place to facilitate the significant increase nestle PNGin capacity to their Tutbury facility.

A new 33kv substation including switchgear, transformes, civil work, earthing etc… was required for the facility expansion and Labron Technical were called in at a very early stage to review design proposals and drawings including protection, earthing and general civil and electrical arrangements.